🧱Concrete Pour Calculator

Calculate concrete volume, ready-mix truck count, and estimated cost from area, thickness, and waste

cm
%
$

How to Calculate Concrete Pour Volume

Accurate concrete estimation prevents the two most expensive pour-day mistakes: running short mid-pour (leading to cold joints and structural weakness) and massively over-ordering (concrete cannot be returned). A few minutes of calculation before calling the batch plant saves real money.

The Formula

Net volume (m³) = area (m²) × thickness (m). Total order volume = net × (1 + waste%). Ready-mix trucks = ceiling(total ÷ 6 m³). Always round up truck count — a partial load still costs the minimum delivery charge, and running short is far more disruptive than a small surplus.

Waste Factor Guidelines

Flat slab on ground: 5%. Elevated slab or footings: 7%. Stairs, curved walls, complex shapes: 10%. Very small pours (< 2 m³): 10–15% because pump residuals become significant. When in doubt, add one extra 5% buffer — it costs far less than a re-pour.

Ordering Tips

Order concrete at least 48 hours in advance. Specify: mix design (strength in psi or MPa), slump (flowability), maximum aggregate size, and admixtures (air entrainment, accelerator/retarder). Confirm delivery time — most concrete has a 90-minute working window from batching.

Frequently Asked Questions

What if I have leftover concrete at the end of the pour?

Ready-mix concrete cannot be returned. Pre-designate a spot for excess — a small footing, path repair, or disposal slab. Brief the crew before the pour so no one adds water to slow setting time (adding water reduces strength significantly).

Do I need a pump truck?

If the truck cannot reach the pour area directly, a boom pump is needed. Add 0.5–1 m³ of pump residuals to your waste factor. Pump trucks typically add $800–1,500 to the total cost and must be booked separately in advance.

How long before I can walk on a concrete slab?

Standard concrete reaches about 70% of design strength in 7 days and 100% (28-day strength) in 28 days. Light foot traffic is possible after 24 hours. Do not load the slab with heavy equipment for at least 7 days. Cold weather (below 40°F / 5°C) significantly slows curing.